|
SUMMARY OF
FINDINGS
download
a Microsoft Word version of this document
| |
|
Introduction
|
The
Rodney District Council has commissioned a report titled "The
PenLink - S 122C Compliance Report".
|
|
|
The
purpose of this section is to create a summarised version of the
full report. This summary includes all major findings but in the
interests of brevity a great deal of material has been omitted.
A reading of the full report is desirable - or at least for sections
of particular interest to individual readers.
|
|
|
The
summary is addressed in the first instance to the newly elected
members (elected March 31, 2001) of the Rodney District council.
|
|
|
This
summary may not completely satisfy everybody - some matters will
be glossed over, others barely mentioned for that is the nature
of a summary. The content of the summary has been a result of the
personal judgements of the writer intended to "hit all the
hot buttons" - to give a clear impression of the essence
of the report and of the issues concerned with the PenLink project.
Fortunately,
any perceived gaps of the summary are covered in the full report.
At the proposed April-May 2001 briefings of the incoming Council,
clarification/amplification of all PenLink related data will be
possible.
The
report has taken considerable time to complete. Field work - research
etc was concluded in early November of 2000. Since that time events
have moved on including, by March of 2001 the withdrawal or settlement
of all Designation and Resource Consent appeals under the Resource
Management Act. References (with earlier dates) in the report to
appeals should be read in the light of later events.
A
comprehensive report concerned with the PenLink project was called
for, based on extensive research and supported with full documentation.
The terms of reference were agreed following considerable deliberations.
|
|
|
Completion
of the assignment culminating in this report has involved a major
commitment of resource including input from RDC senior management
and the RDCs professional advisors.
|
|
|
At
the outset, it is appropriate to record that at all times the assistance
given the writer, both in compiling research material and responding
to all enquiries has been unstinting and supportive. This has been
most appreciated.
|
|
The
Importance of Penlink
|
The
efforts of those involved in this exercise signals the importance
of the assignment to the RDC. Its importance can be attributed to
the following two matters:
- The
PenLink project, its Weiti River bridge crossing, its associated
roading and the complimentary widening of Whangaparaoa Rd is the
largest and most complex project the RDC has to date dealt
with. This is true of its capital cost of $70 M and because
the proposed BOOT-type funding and management contractual arrangements
involving private sector funding are for large sums of capital
expenditure associated with commitments which will be put in place
for the very long term.
|
|
|
- Arising
from the previous councils demise, a vacuum of current
knowledge concerning PenLink amongst decision-makers, (the Council
to be elected in March of 2001), has developed. The newly elected
council will have to be "brought up to speed" and be
fully briefed about PenLinks plans - plans put on hold for
over 15 months.
|
|
|
[Notes;
The term PenLink - more recently "PENLINK" is a composite
word denoting the Whangaparaoa Peninsula Link. PenLink
has also been known as "The Weiti Crossing". "S 122C"
is shorthand for S 122C(1)(c) - primarily the benefit-cost requirement.]
|
|
|
Progress
with the concepts, design and consents for the project together
with public consultation on PenLink is well advanced. Councillors
will discover that the ground has been very fully prepared.
All
that remains is for discussions and debate of the project to be
held, and for a "go-no-go" decision - that is the decision
to proceed or not with PenLink to be made.
The
go no-go decision relates to the decision to proceed. It
does not finally commit the RDC, as there are a number
of points at later dates at which PenLink as proposed may be discontinued.
|
|
|
The
Rodney District Commissioner, Mr G Kirby explicitly stated within
the terms of reference for this assignment that one of the main
objectives of this report was "to fully inform the new
Council" about PenLink.
|
|
|
Given
the projects significance, the new Council needs to be fully informed
on these matters and very significant effort and expense has been
associated with the projects preliminary plans. It is intended therefore
that in the interests of saving the costs of re-performing these
steps, that credit should be taken for past efforts - and used as
a basis for future decisions. This report is presented in evidence
to support this objective - to seek "buy-in" from elected
members for the decisions taken already.
It
is important to state though, that the "buy-in" should
result from an informed and balanced consideration of the pros
and cons of the project - to avoid any hint that the new Councils
decision is in any way "pre-determined".
|
|
|
The
task of informing the new Council about PenLink also includes full
consideration of the reasons for earlier decisions, appreciation
of the risks involved, mature reflection - if need be a robust debate
all leading to a decision to proceed or not with PenLink as proposed.
|
|
|
At
an early date, scheduled for May of 2001 elected members will be
asked whether they wish to proceed with PenLink, (the so called
"go-no-go" decision). Their consideration of this report
and other related reports should form the basis for reaching a decision.
|
|
Nature
of the Task
|
The
title of the report of this assignment includes a reference to S
122C of the Local Government Amendment (No 3) Act. The terms of
reference for the assignment were based on this legislation
which is designed to promote sound, prudent and informed financial
management decision-making. Full information should be provided
to decision-makers to assist them to make sound financial management
judgements.
|
| |
The
Act however is non-prescriptive as to its information requirements
- for whilst suggesting a form of "benefit cost" analysis,
the Act contemplates a number of different methods by which to reach
the goal of making good policy and financial decisions.
|
| |
Various
authoritative sources provided assistance for this assignment in
setting its scope and in the design of a process to meet these objectives.
These objectives are most clearly stated by the Society of Local
Government Managers - ("SOLGM") - in their "Good
Practice" Guidelines: [ref; 2010202]
|
| |
The
guidelines emphasise the need to consider all matters relevant
to an assessment including consideration of alternatives:
|
| |
"Statutory
principles require a different approach to good practice guidance
from that for procedural and machinery requirements. Principles
are directly concerned with what is done rather than
how. Therefore consideration of costs and benefits as
set out in S 122C(1)(c) of the Act is fundamental to good policy
making. This allows decision-makers an informed choice from
a range of alternatives.
Decisions
cannot comply with the principle unless decision-makers are
aware of options and their relative merits and drawbacks.
The formal presentation of this information in reports ensures
that the principle can be complied with.
A
secondary consideration is that this also provides prima facie
evidence of legislative compliance."
|
| |
The
terms of reference of this assignment [ref; 2000925] as set
out by the Rodney District Councils Commissioner are fully
consistent with these guidelines. The Commissioner required for
the PenLink project, preparation of:
|
| |
- Which
would fully inform the new council and
- Would
document actions already taken as part of a defensible and documented
process."
|
|
The
Report
|
To
meet the documentation requirements, the full PenLink S 122C report
has been completed as follows:
|
|
|
- Volume
I - the principal "Report" commences with this Summary
of Findings, followed by an introduction, the content of which
has already been briefly described in this summary. The remainder
of the report comprises a further eight sections dealing with
various topics - some of interest for their concepts - (Process),
others for use in documenting the history of the project - (History
and Consultation).
|
|
|
The
final section, titled Decision Points and Project Briefings provides
readers with a schedule of tasks, actions and their dates planned
to further the progress of PenLink.
|
|
|
Topics
for the report have been carefully selected. The basis for their
selection has been designed to reach a balanced, independent and
informed position on all matters of relevance to the project.
The writers research has been wide-ranging and relatively
unrestricted. In the course of the investigations associated with
this assignment, various important issues and matters of public
interest were identified. These are summarised in the section
titled Technical Engineering and Related Compliance "Issues".
As
a result of the research and deliberations the following topics
were chosen for inclusion in this report.
They
are:
- Introduction
and Terms of Reference
- History
of the Project
- Processes
- Consultation
- Funding
- and other related (S 122C) compliance matters
- Technical,
Engineering and Related Compliance "Issues"
- Legislative
Requirements
- Financial
Analysis
- Decision
Points and Briefings.
|
|
|
A
glossary of terms used in the report accompanies this volume.
|
|
|
- Volume
II - Appendices. This volume commences with a "Roadmap"
describing the hierarchy of research material, documentation,
appendices and references associated with the report. This is
designed to assist readers in their identification and understanding
of how the components of the report all fit together.
Next
follows the full index or research database which is titled "Chronology
of Events and Bibliography" - the title and its frontpiece
describe its functions and workings. A list of those persons interviewed
for the assignment is also included. Then follows texts in appendice
form for all references quoted as "extracts" and contained
in the body of the Volume I report.
|
|
Major
Points Raised Within the Report
|
The
following information of this "summary" section of the
report encompasses the content of the full report. For each
section, in most cases the "topics" chosen are first explained,
then the major significant findings for each area of interest connected
with the topic are briefly recorded.
|
|
|
Caution:
This summary is not a substitute for a full reading of the report,
particularly for matters of complexity, as these require a full
and careful analysis. The detail of the full report supports each
finding and these particulars may be readily studied by readers
who wish to be fully informed on any particular subject.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Introduction
and Terms of Reference (Section 2)
|
The
purpose of Section 2 (Introduction and Terms of Reference) of the
report is to describe the nature and terms of engagement for the
assignment, particularly the legislative basis for its conduct.
The
overriding objective - of "a S 122C report" as described
in the legislation is "the promotion of prudent, effective
and efficient financial management by local authorities".
|
The
basic (S 122C) objective was extended for this assignment by the
Commissioner to include broad informational and documentary purposes.
|
|
|
The
PenLink project is a proper candidate for a project-related benefit
cost study.
|
This
is due to its significance both in terms of the size of expenditures
and the long-term commitments involved.
|
|
|
In
the view of the Auditor General, a S 122C compliance report
encompass assessments of costs and benefits of a non-financial
nature including policy and political considerations. SOLGM
guidelines point to the need for a comprehensive S 122C assignment
to consider alternatives. (See also comments above.)
|
A
balanced and objective report is necessary to promote good decision-making.
This will involve a consideration of alternatives to any proposal.
|
|
|
The
PenLink project as planned is well advanced, decisions have already
been taken concerned with the projects design, properties
have been purchased and the proposed funding - a BOOT-type (Build
Own Operate and Transfer) contract is being
developed. Legislation is being promoted to enable PenLink to be
a tolled facility. The current RDC Annual Plan reflects these decisions.
|
The
newly elected Council will be faced in May 2001 with making a "go
no-go" decision concerning the PenLink plan.
|
|
|
The
assignment has been conducted mindful of the recent events which
saw the previous Council replaced by a Commissioner. These events
have affected progress with PenLink and of particular significance
to this report is the need for newly elected (March 2001) members
to be fully informed on matters concerned with the project.
|
It
is a clear intention of this report to elicit the "buy-in"
of decision-makers (elected members) relating to past decisions.
Credit is intended to be taken, (in the interests of cost savings
by not reperforming the steps) to progress PenLink. This intention
is a reasonable one provided elected members are still free to reach
their own appropriate decisions.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Section
2 (continued)
|
A
balanced report should include reference to the views of those who
oppose the project. The core of remaining opposition - the level
of which has markedly declined since PenLink was first proposed,
remains (not unnaturally) the objections of those directly affected.
These persons are in the main, some residents of Stillwater.
|
The
major social impact of PenLink has been identified as affecting
some property owners in the Stillwater area. The trade off of benefits
from PenLink for "the many" will be offset by the costs
to "the few" who will suffer losses because their properties
are proposed to be taken. Elected members need to carefully weigh
this situation when evaluating the projects benefit and costs.
|
|
|
The
S 122C reports objectivity has been influenced by the need
to preserve commercial confidentiality confined to financial
details of the BOOT-type bid tendering process. The level of
confidentiality that is acceptable concerns the fine detail of the
proposed tender. It does not extend to full discussions by
elected members of matters concerning the merits of PenLink when
compared to the alternatives to it.
|
To
maintain the necessary competitive tensions within the tendering
process it has been necessary to restrict the level of detail that
can be made public concerning the BOOT bid. There are sound reasons
for following this course - in spite of the risk of any claims that
"the public interest" requires fuller disclosure. This
view is supported by an opinion of the Councils legal advisors.
|
|
|
PenLink,
is by New Zealand Local Government standards a very challenging
and unconventional project. The writer (after considerable research)
is unaware of any similar project that consists as does PenLink
of all of the following inter-related components:
- "relatively"
low value - less than $100 M
- a
pilot scheme with its associated learning curve for the components
involved
- a
need to sponsor special "local" legislation
- BOOT-type
funding and
- proposed
tolling of the facility using advanced tolling technology.
|
The
combination of all of these factors places very significant demands
on the Council. Whilst there is clear evidence from both RDC management
and their professional advisors of a determination and a demonstratable
competence for "getting it right", elected members should
be left in no doubt that PenLink as proposed poses major challenges!
|
|
|
FINDINGS
|
COMMENTARY
|
|
History
of the Project (Section 3)
|
The
History section of the report is a "potted" version of
key events taken from the full research database. Selection of these
"key" events, demonstrates the evolution of PenLink. The
notion of a tolled "Weiti Crossing" commenced with private
sector interest in "the eighties". Council developed its
own strategies in the growing knowledge that:
- the
Whangaparaoa Peninsulas traffic woes would progressively
worsen
- the
widening of Whangaparaoa Road alone would have severe social impacts
and high costs - without any Transfund subsidy (which based on
present information indicates that PenLink would not qualify for)
- a
BOOT-type private sector funding, construction and management
of a tolled (PenLink) facility was planned
- subject
to the conduct of all necessary RMA and other steps to assess
the effects of its plans, a Weiti River bridge would be necessary
and
- the
RDCs borrowing limits would "prevent" the Council
from funding a Weiti crossing project.
|
The
evolutionary nature of the PenLink project can be discerned
from a review of its history. The Council did not start out
with its mind made up.
The
chapter of events recorded by this section of the report supports
later conclusions "that no decisions were pre-determined",
that "consultation has been extensive" and all preliminary
procedures/processes required to date for PenLink have been conducted.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Processes
(Section 4)
|
This
section is intended to meet some of the informational objectives
of the assignment in so far as they relate to the "Processes"
associated with PenLink.
The
section identifies six separate - though interrelated - processes:
- Councils
operational (process)
- Councils
democratic
- RMA
related
- PenLink
technical-engineering related
- BOOT
tendering
- Consultation
(- the next section of the report is devoted to a full coverage
of these processes).
|
Whilst
much of this section is merely a matter of record and of information,
the parts relating to the BOOT tendering process are of particular
significance. The BOOT process in this report is described in as
simple terms as possible - in spite of the complexities involved.
It is important for elected members to appreciate the mechanics
of the process as later sections - for example Financial Analysis
are based on knowledge of how BOOT contracts operate.
|
|
|
The
concluding part of this section describes the steps which the PenLink
project Working Party (a group comprising RDC engineering staff
and professional advisors) is following to implement the BOOT arrangement.
|
The
description of the BOOT process includes steps that lead to the
"go-no-go" decision of newly elected members - scheduled
for May of 2001.
|
|
|
There
are further democratic processes in the pipeline. Approvals to proceed
further with the project are being sought, following which the later
BOOT and other processes will be progressed.
|
Consideration,
of this "S 122C" report (and others) are important elements/steps
in the democratic processes associated with PenLink.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Consultation
(Section 5)
|
This
(large) section - it comprises about one-third of the total content
of Volume I of the report has the following two objectives:
- to
meet the Commissioners infor-mational requirements and
- to
establish the comprehensive nature and thereby the legitimacy
of all consultation processes already completed.
|
A
very detailed report of consultative events was called for. Research
has established that Consultation has been extensive - as
an expert witness within the RMA process put it "the most
intense and comprehensive conducted for a major infrastructure study
in the Auckland region to date" [ref; 980805.5]
|
|
|
The
"consultative" events described, show how public opinion
initially "loud and opposed" to PenLink has gradually
evolved to the present point where "two out of three"
of those surveyed ("R Cubeds September 2000 survey) [ref;
2000901] are in favour of PenLink.
The
findings of the survey however need to be judged within a context.
The context involves the fact that the public opinion survey for
PenLink as proposed was "at no cost to ratepayers" and
affects "only the residents of the Hibiscus Coast area".
|
The
record shows that the RDC has covered all of its (consultative)
bases.
Elected
members are entitled to rely on this evidence. This will significantly
contribute to their "buy-in" for the PenLink project.
(Note:
Should the context change - for example if the HBCs Area Committees
constitution alter, then survey and other findings could be invalidated.)
|
|
|
FINDINGS
|
COMMENTARY
|
|
Funding
-
and other related (S 122C) Compliance Matters (Section 6)
|
This
section records the RDCs adherence to and compliance with
the financial management and funding provisions of the Local Government
Act. At this time many of the provisions are either only partially
completed or may not be relevant. Those that are not presently relevant
include funding provisions relating to borrowing which if the proposed
BOOT funding is put in place will not become operative.
|
Subject
to the caveats concerning applicability or relevance, the funding
requirements of the law to date have been complied with.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Technical,
Engineering and Related Compliance "Issues" (Section 7)
|
This
section whose title "Technical, Engineering and Related Compliance
"Issues"" may be something of a misnomer, is a repository
for the issues which require airing concerning PenLink, -
"Technical" sounds better than "Repository".
This
section has been included to give a focus for elected members by
identifing matters which form part of a comprehensive debate
about the merits of PenLink. Some, but by no means all, are
matters which have already been "decided" -subject however
to ratification by the new Council.
A
balance needs to be struck in considering past decisions, a balance
between taking credit for these actions and on the other hand risk
reopening the inquest. The risk exists that to accept earlier decisions
without proper informed discussion and reflection may lead to claims
of pre-determination. On the other hand, too widespread and poorly
focussed a debate may prejudice the valid acceptance (buy-in) of
much of what has been achieved, (for example the RMA designation
and consents processes).
|
The
matters raised should be aired at the (Apri/May) 2001 briefing of
new Councillors.
The
RDCs professional advisors must respond in a satisfactory
manner to Councillors enquiries. The stakes are too high to accept
any less.
The
highly summarised form of the issues listed, merely addresses the
key questions without any accompanying and detailed points of clarification.
[Note:
There can be few if any claims of commercial confidentially made
concerning these issues. Most relate to risk assessments which need
to be made and settled before a decision to proceed with PenLink
can be considered.]
|
|
The
matters (the "Issues") raised include - in synoptic form:
- Is
PenLink feasible?
- Is
Penlink going to be "the best deal" for the Rodney District?
- What
would be the alternatives to PenLink?
- What
are the financial consequences of
- PenLink
- Its
alternatives.
|
Full
discussion of these issues will assist in elected members reaching
their views.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Section
7 (continued)
|
There
is one issue raised within the "Technical" section which
deserves to be highlighted. It is the question of the potential
loss of ratepayer value arising from loss of the Transfund Subsidy.
In normal circumstances this subsidy - of some $24 M would be paid
by Transfund as their share of the costs of a Weiti Crossing and
other related roadworks. It should be noted that the Crossing and
other works meets Transfunds subsidy benefit/cost criteria.
Ratepayers,
via their petrol and road user charges have contributed to Transfunds
coffers but present plans do not involve payment to the RDC of any
Transfund subsidy for PenLink. The unconventional nature of the
projects funding appears to preclude the prospect of receipt
of the RDCs entitlement to a Transfund subsidy. Some "quid
pro quo" for this would seem warranted.
|
A
full and informed discussion on this matter is necessary to enable
elected members to reconcile their views on this matter.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Legislative
Requirements (Section 8)
|
The
PenLink project cannot proceed unless the RDC is given the
appropriate legislative authority. The Councils legal advisors
and others are working with advocates (the local MP and others)
and law draughtsmen to produce a (PenLink) Local Parliamentary bill.
Authorisation
is needed to - inter alia:
- permit
tolling
- allow
the RDC to lease the PenLink land to the BOOT operator and
- to
permit PenLink to be operated "cheek by jowl" with connecting
local roads and State Highways.
|
PenLinks
legislative processes/
permissions must be satisfactorily concluded before it proceeds.
Gaining legal authority is therefore a condition precedent
to the letting of any tenders which recommences "the full PenLink
process".
|
|
|
Present
indications for the Local Bill appear auspicious and good progress
toward gaining legal permission is being made.
However
the present Governments policies include an intention to "introduce
wide-ranging roading reforms.
Should
the RDCs-PenLink Bill become "entangled" in the
Governments own initiative, then it is not inconceivable that the
RDCs process could be overtaken or superseded.
Equally
there is the prospect that PenLink could lead the way and precede
the Governments wider initiative.
|
There
is a risk of "a collision" between the two legal processes.
Only time will tell whether these concerns are realised or not.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Financial
Analysis (Section 9)
|
KPMG
have been retained as the Councils financial advisors. As
part of the AEE processes conducted by Becas, financial
analysis was conducted early on by KPMG relating to PenLink. Becas
findings were analysed by KPMG who also conducted their own modelling
and further study of the financial circumstances of the project.
KPMG have also taken a leadership role in specifying the protocols
governing the proposed BOOT-bid - the tender round. To date these
matters are well advanced - but they can only be proven to operate
as intended when they are implemented.
|
A
full reading of this section of the report is strongly advised,
as it is an area of both detail and complexity.
The
process used (and described under "Processes" in this
report) is based on overseas experience of "similar" projects.
The process is all-important to a satisfactory outcome, as it (the
process and its systems) are designed to simulate a competitive
environment by having competing tenderers follow a process which
will create "competitive tensions".
By
these means the RDC is endeavouring to achieve the "best deal
possible".
|
|
|
The
objectives of the KPMG financial analysis were:
- to
establish if the project was "feasible" or not - with
this test relating to whether the private sector would be "likely"
to enter into a BOOT contract with the RDC.
KPMG
established that the project was feasible and that private
firms would be attracted to the prospect.
- to
determine "benchmark" financial criteria - known as
"the Financial Internal Rate of Return - (FIRR)". As
part of the tendering round the benchmark FIRR would be used to
evaluate tenders to enable a determination to be reached assessing
if the RDC would get "a good deal" or not.
|
The
financial analysis has been conducted as circumstances dictate on
an analytical basis and is based on estimates which involve the
use of judgements. Until the BOOT-bid process is completed the outcome
of the process and the validity of the assumptions of the analysis
will be uncertain. The process is intended to deliver the best deal
possible and such an outcome is expected to ensue.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Section
9 (continued)
|
Certain
"confidentiality" restrictions have, (based on legal advice)
been placed on the detail of PenLinks financial arrangements.
Provided that these restrictions are not unreasonable and are confined
to "financial detail," confidentiality is justifiable.
It is justifiable for the reason that its disclosure could provide
tenderers with information that would have the potential to invalidate
the BOOT-bid process.
Public
concerns expressed relating to commercial confidentiality are therefore
largely misplaced. Comfort for decision-makers - to compensate for
some lack of knowledge, can be gained from the involvement of people
- (professional advisors) and the integrity of the systems - (the
BOOT-bid process). Both are factors intended to achieve a good deal
for the RDC.
|
The
particulars of the confidentiality issue are covered in more detail
in the body of the report. One consequence of this issue is that
considerable reliance is placed on the RDCs professional advisors
- principally KPMG. (See also the next point - below).
|
|
KPMG
have given no assurances that their views, stated in considerable
detail as conclusions of the Financial Analysis section should be
taken as representations or opinion. They have requested that their
views be characterised as observations.
|
The
combination of:
- the
considerable reliance to be placed on the evidence of the RDCs
professional advisors - in part as a result of a lack of detail
(withheld for reasons of "commercial sensitivity") and
- KPMGs
level of "assurance" for their evidence - termed "observations"
signals to elected members the importance of their own
assessments concerned with the financial arrangements of PenLink.
|
|
|
Elected
members can take considerable comfort in the final event, as the
process for the BOOT-bid provides a safeguard for this exposure.
The BOOT-bid will not proceed to contractual terms unless
the final evaluation process (concerned with the one preferred
tenderer) meets the RDCs benchmarked and other criteria.
Right up to this point the RDC are not committed to PenLink.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Section
9 (continued)
|
Risk
Analysis and risk assessments were conducted by KPMG. KPMG carried
out extensive investigation and documented their findings in their
"Risk Matrix" [ref; 980301.4 & 980301.5 et
al] document.
This
document identified the risks associated with PenLink. For differing
scenarios, including the RDC "doing" PenLink itself, KPMG
determined which party would carry each risk. Later versions of
the document dropped the "RDC doing it option" as it was
recognised that:
- the
RDC did not consider that its funding base (financial and borrowing
capability) allowed for it to fund the project and
- the
major justification for private sector (BOOT-type) funding was
the transfer from the RDC of risks. The risk of future operating
losses was highlighted as the principal exposure whilst the risk
of for example, cost overruns for construction costs was considered
to be secondary.
|
There
is little doubt that the transfer of risks to the private sector
is a, (possibly the most) significant motivation for the
proposed PenLink financial arrangements. Public sector long-term
projects involving large capital expenditures do not historically
have a great track record. Given this history, even if the RDC were
to demonstrate with some certainty that it could do PenLink itself,
the exposures the RDC would in that event face might prove too daunting
to embark upon.
Though
no complete data has been provided of the RDC "doing it"
option it seems that the view that the RDC could not "do
it themselves" is not the full picture. For if the revenues
from tolls more than offset the costs of servicing PenLink
debt and other operating costs then the RDC "could do it".
This
intriguing possibility should be explored further. "On the
other hand," a shortfall of toll revenues over debt costs might
be revealed and the risk-shedding to the private sector would then
be seen "in relief," - as desirable - as would the possibility
of receipt by the RDC of any concessions from private investors.
Amongst
the consideration of alternatives to PenLink, these matters
rank very highly.
|
|
|
Some
residual risk would remain in "the RDCs care" if
PenLink proceeded. Certain non-insurable risks associated with government
actions and force majure (earthquakes, tsunamis etc) will
not be carried by the BOOT operator.
|
Most,
though by no means not all PenLink risks will be the responsibility
of the BOOT operator. The RDC would probably need to cover the uninsurable
risks including exposures for the BOOT operator arising from (central)
government actions.
|
|
|
FINDINGS
|
COMMENTARY
|
|
Decision
Points (Section 10)
|
This
section of the report catalogues the steps scheduled from the present
- (2001) to completion - (2005) of PenLink.
|
This
schedule will be of use to orientate elected members and to signal
the challenges and decision points for the future.
|
|
A Final
Summary - of Summaries
|
Readers
of the report (or of merely this first section - "Summary of
Findings") will draw their own conclusions upon the issues
traversed throughout the report. A summary of all of these matters
would be a daunting if not an impossible task. The pros and
cons of any assessment of the merits of the PenLink proposal are
too varied and complex to reduce to simplistic terms or to be conveyed
in a highly summarised state.
|
|
|
But
what can be attempted is to reach a few major and overall conclusions
that are a combination of "positions" reached - based
on the evidence and also those observations that are supported by
applying common sense and logic - or at least the writers notions
of these!
|
|
|
None
of the conclusions are couched in absolute terms. Decision makers
must still reach their own positions on these matters. Nevertheless
the following overall conclusions, it is submitted are well founded
and are made in expectation that their documentation is the least
that could be expected from the writer of this report after
such a prolonged, rigorous and detailed investigation.
|
|
Conclusion
1
|
There
seems little doubt that a solution to the traffic woes of the Whangaparaoa
Peninsula is needed - and soon.
|
|
|
Public
support for a solution is solidly in favour of a Crossing. The
recent R Cubed public opinion survey conclusively indicated
that "Roading, congestion and access are the most important
issues on the Coast". Other alternatives (without a bridge)
are viewed as being too disruptive of community interests - householders
on the peninsula would be very affected by any major
road widening plans. Widening of Whangaparaoa Road alone could
be prohibitively expensive - as presently this would not qualify
for a Transfund subsidy.
|
|
Conclusion
2
|
Public
support for the PenLink proposal based on the recent "R Cubed"
survey favours the PenLink proposal - but the context for this support
needs to be clearly stated;
|
|
|
"Support
greatly outweighs opposition given the basic concept. Without
costs mentioned, support dropped and opposition rose after
the cost implications and toll were explained."
|
|
|
"cost
effectiveness is the biggest driver of support or opposition."
|
|
|
Perceptions
of costs (not unnaturally) have influenced the surveyed publics
view of PenLink. On balance though, a majority of the public appear
to support the proposal for a bridge funded from bridge user
tolls. [ref; 2000901.2 et al]
Opposition
to a bridge is now more muted. Note however that this does not
lessen the vehemence of opposition from "the few" -
those who will be directly affected. Elected members must decide
for themselves whether the costs to be borne by these persons
are acceptable.
|
|
Conclusion
3
|
The
RDC has been scrupulous in impeccably following the highest standards
of all process related matters. The solidity and comprehensiveness
of these procedures justifies reliance upon the outcomes already
reached and resulting from them.
This
extends principally to the extent and quality of all consultation
steps, adherence to all RMA and other regulatory, enabling and
legislative provisions. The proposed BOOT-bid process is intended
to deliver a "good deal" to the RDC.
|
|
Conclusion
4
|
The
proposed (BOOT-type) funding for PenLink is a proper financial/funding
mechanism that the RDC is authorised to implement.
|
|
Conclusion
5
|
Before
PenLink may proceed, all appropriate legislative permissions and
other terms and conditions need first to be in place.
This
principally relates to the passing of the Bill authorising PenLink
to proceed.
|
|
Conclusion
6
|
Alternatives
to a BOOT-type funding mechanism should be considered. An informed
and robust debate is warranted for these matters that include:
|
|
|
- consideration
of the merits and disadvantages of the RDC funding the project
itself including the consideration of the relative risks and the
rewards of an RDC-self-funded option. The prospect of the RDC
carrying the risk of future operating losses will be prominent
in these considerations.
|
|
|
- consideration
of the "loss" of the Transfund subsidy
|
|
|
- consideration
of the challenges presented by PenLink as proposed to the RDC,
the implications of a BOOT-type contract including those related
to its tendering, its contract management, its long term "lock-in"
effects and the receipt of appropriate assurances from the RDCs
professional advisors.
|
|
|
Consideration
of these matters will assist decision-makers in reaching an informed
view on the nature of a "good deal" for RDCs ratepayers.
|
|
Conclusion
7
|
A
"good deal" for the RDC will be achieved:
|
|
|
Firstly
- following an assessment of all alternatives (conclusion
6 above)
|
|
|
Secondly
- completion of the PenLink project bid process and
comparisons with the best bid from a BOOT tenderer
|
|
|
Thirdly
- assessment of the best bid against RDC benchmarks.
|
|
|
The
decision to proceed or not with PenLink as proposed will follow
these deliberations. The outcome (whatever it is) of the process
described will be derived from robust medium-risk strategies which
will, when they operate as planned lead to appropriate and defensible
financial decision-making.
|
|
Conclusion
8
|
Newly
elected members, fully informed on the matters concerned with PenLink
must be comfortable with the PenLink proposal prior to making in
May of 2001 the "go-no-go" decision.
All
of the relevant S122 (1) (a) to (f) criteria are presently met.
At the time that the final decision is made, these criteria (and
more current financial projections) will require reconfirmation.
Larry
N Mitchell
Public Sector Finance & Policy Analyst
Puhoi 1243
Northland
March
16 2001
|
|
|