PENLINK FINAL
S 122 C REPORT
Events affecting
PENLINK and occurring since November 2000
A tabulation of subsequent
events and commentary
The investigation
and draft reporting of events associated with the PENLINK project
had a "cut off" of November 2000. This section of the report
records the events of significance to the project that have occurred since
that date and up until February 2002.
The process
of completion - closure for this assignment - was a subject for discussion
between the CEO, councillors and the writer. Selection of the best time
to complete a final report was an important issue so that the best value
possible could be obtained from the exercise consistent with the need
for both completeness and timeliness.
Advice was
sought in September of 2001 from the Office of the Controller and Auditor
General, (the OAG) relating to the manner in which this final report should
be completed. S 122C, the general provisions of the Act and the SOLGM
guidelines which were used to determine the terms of reference for this
assignment made no mention of the manner in which closure could be achieved
and reporting responsibilities completely discharged.
The difficulty
with S 122C responsibilities is that reporting of the events and issues
concerned with a project or proposal deal with over time "a moving
target". The events concerned with PENLINK have been very protracted
as is evidenced from the draft report that covered a period of at least
five years, from 1995 to 2000. A further fifteen months have elapsed to
date since the draft report was prepared.
The OAG advised
that a convenient and timely final reporting point should be chosen and
the report completed at the date selected. The final report should address
all outstanding issues irrespective of their stages of resolution. It
would then be the responsibility of the Council, to whom the report is
addressed to resolve any outstanding issues or to at their discretion
resolve any further uncertainties.
A convenient
time to issue a final report has been chosen. February 28th 2002 is the
date selected, principally because it will have allowed elected members
following their election in March of 2001 sufficient time to "come
to grips" with all of the issues. The February 2002 date also allows
the Council sufficient time to properly address all outstanding issues
before the PENLINK contract is signed, at present this is scheduled for
"June-August 2002".
The following
table factually records the significant events that have occurred since
the date of the draft report. A brief commentary for each event is added
and these reflect, where appropriate any further issues arising from them.
This section
of the report concludes with more expansive commentary of issues arising
from the subsequent events.
PENLINK significant
events- since November 2000 to the present.
|
Event date
and reference
|
Nature of
Event
|
Commentary
|
|
14
May 2001
|
Draft
PENLINK S 122C Report - Author Larry N Mitchell
|
This
report was delivered to Councillors on 14 May 2001 - prior to the
31 May Council Meeting for their consideration.
|
|
21
May 2001
|
Special
Council (workshop) Meeting [ref; 123/5/01]
|
This
was a workshop to which the public was admitted that briefed the
new Council on the PENLINK project. Members of the project team
were in attendance and they answered Councillors queries. Numerous
issues raised were documented and responded to including a response
from KPMG (Risks) and Simpson Grierson (Council liability for further
market research).
|
|
29
May 2001
|
Memo
from Project Manager of PENLINK to Mayor and Councillors
[ref;
RF/53/2]
|
Councillor
Walker had raised 20 questions during the course of the 21 May workshop.
The Council's professional advisors responded to these and they
were circulated under the cover of the memo. The responses included
a report of GMD Management, Engineering and Environ-ment consultants
titled "Report on Traffic Capacity issues West of Vipond Road" dated
July 2000.
|
|
31 May 2000
|
Council
Agenda paper and attached report from John Brown - Project Manager
- PENLINK dated titled "PENLINK Access to Whangaparaoa Peninsula
[ref;
RF/53/2]
|
This
very detailed report stated its purpose to be "To enable the Council
to make an informed decision on whether to proceed with PENLINK
(Weiti Toll Road)." The "package" of papers presented included:
- Memo
from J Brown
- The
"Designation" decision
- The
consent orders and their conditions
- The
map of the proposed route
- The
draft Empowering Bill
- The
land purchase requirements
- Pages
4 & 5 of Section 7 of the Larry Mitchell Draft S 122C report
- the "Issues enumerated"
Responses
from KPMG, Beca Carter and Simpson Grierson to the S 122C "Issues".
|
|
31 May
2001
|
Decision
of Council at their Council Meeting
[ref;
RF/53/2]
|
This
decision stated:
- That
the report be received.
- That
the Council affirms its support for proceeding to the next stage
of the project.
- That
the Council call publicly for Expressions of Interest in the project
as the first step in the tender process.
- That
the Council proceed con-currently with the processing of a local
Bill to enable the development of the toll road by private enterprise,
the Bill to be sponsored by the local Member, the Hon. Dr Lockwood
Smith.
- That
the Council re-iterates its commitment to encourage local employment
and traffic minimisation.
- That
the Council prepare a "fall back" option for the relief of Whangaparaoa
traffic congestion to be implemented in the event that the PENLINK
project cannot be proceeded with on terms acceptable to the Council.
|
|
26 July 2001
|
Report
of Wayne Donnelly - Chief Executive of Rodney District Council to
the Council titled "PENLINK Tender Process - Evaluation Team"
[ref;
RF/53/2]
|
This
report suggested suitable persons, (with CVs) to form the project
evaluation team.
|
|
26
July 2001
|
Other
Reports/Papers associated with Appoint-ments of Evaluation Team
Members [ref; RF/53/2]
|
A seven-person
evaluation team was appointed as approved by the Council at its
26 July 2001 meeting.
|
|
26
July 2001
|
PENLINK
Progress report from John Brown to Councillors for the 26 July 2001
meeting [ref; RF/53/2]
|
This
report (reporting progress on the project) included information
relating to:
- expressions
of interest
- legislation
- land
purchases
- the
S 122C Compliance Report
Included
also was a copy of a letter (W Donnelly to Cr W Walker) giving further
details relating to traffic volume projections. The view was expressed
by the CEO that the traffic volume evidence as supplied was consistent
with projections used for the Council's project traffic volume calculations.
|
|
26 July
2001
|
Decision
of Council
[ref;
RF/53/2]
|
The
PENLINK progress report was received and the Council resolved to
hold a half-day workshop to discuss the issues of the Draft S 122C
report.
|
|
26
July 2001
|
Report
to and Resolution of council re Appointment of the PENLINK Probity
Auditor [ref; RF/53/2]
|
(Procedural)
A probity
auditor (as recommended) was appointed.
|
|
30
August 2001
|
Supplementary
Agenda Report of Bill Horne (RDC Special Projects Manager) Titled
"Access Alternatives" [ref; RF53/2 & RF54/1]
|
The
report's purpose was to evaluate certain "fall back" options if
PENLINK did not proceed. This arose from Councils 31 May 2001 meeting
at which it was resolved "to prepare a fall back option."
|
|
17
September 2001
|
Agenda
Paper and Report from John Brown re Expressions of Interest Protocols
[ref; RF/53/2]
|
(Procedural)
|
|
17
September 2001
|
Minutes
of Decision to Approve the Protocols for Evaluation of PENLINK Expressions
of Interest.
[ref;
RF53/2 & RF/53/4/1]
|
(Procedural)
|
|
17
September 2001
|
Report
and Appendix 5 from John Brown Titled "Submission to Select Committee"
[ref;
RF53/2 & RF54/1]
|
The
purpose of this report was to "obtain approval for a submission
to the Parliamentary select Committee considering the Bill".
|
|
17
September 2001
|
Minutes
of Special Council Meeting Appointing the Mayor to Present its Submissions
to the Select Committee.
[ref;
RF/53/2 & RF/54/1]
|
The
minutes record the approval of a majority of Council to the appointment
but five Councillors (Crs Rose, Smith, Walker, Foster and
Harding) recorded their opposition on the grounds of:
- misleading
information contained in the explanatory note to the Bill and
- because
the submission had not been debated and
- because
of insufficient time/
restrictions upon debate.
|
|
27
September 2001
|
Notice
of Motion re PENLINK project tendered by Cr W Walker.
[ref;
RF/53/2 & RF/54/1]
|
Eight
points raised by Cr Walker resulted in the Council agreeing to two
matters:
- regular
(monthly) PENLINK expenditure reporting and
- reasonable
time being allowed for public and Councillor digestion of future
PENLINK reports.
|
|
8 October
2001
|
Confidential
Minutes Relating to a Special PENLINK (Workshop) Meeting
[ref;
RF/53/2 & P 274]
|
This
special workshop afforded the writer (Larry Mitchell) the opportunity
to discuss the content (in particular the "sixteen questions") of
his draft S 122C PENLINK report. Discussion at the meeting
lead to commissioning of a study to "report upon an "RDC/DIY" option.
|
|
15
October 2001
|
Dispatch
of email to Group Manager Finance and Support Services specifying
terms for the preparation of a "Public Sector comparator".
|
To
satisfy the requirements of the S 122C analysis this email
outlined the suggested terms of reference for a study into the (principally
financial) implications of an RDC/DIY option - as a possible alternative
to a BOOT funded PENLINK.
|
|
25
October 2001
|
Agenda
Paper - "PENLINK Expenditures 2001/2002"
|
John
Brown - Project Manager PENLINK reported current Annual Plan budget
approvals for PENLINK totalling $740,000. Expenditure to date (30/9/01)
$210,550.
|
|
25
October 2001
|
Agenda
Paper - "PENLINK - Expressions of Interest".
|
Consideration
of recommendations of a short list of tenderers determined by the
PENLINK evaluation process.
|
|
25
October 2001
|
Agenda
Paper - "Alternatives to PENLINK".
|
The
collection of papers associated with this Council Meeting agenda
item included:
- The
CEO's views resulting in his submission to Council (which was
accepted) that "there is in fact little value to the community
in examining further alternatives to PENLINK."
- A
suggested brief for the alternatives study - not proceeded with.
- A
submission by Cr Walker on the matter of alternatives.
- A
record of an address given at the meeting to councillors by the
Stillwater R&R Association.
- Minutes
of all of the above.
|
|
25
October 2001
|
Notice
of Motion - Cr Walker - PENLINK
|
Cr
Walker moved a number of motions relating broadly to his request
for further information being made available - for example the "Toll
Response Modelling Report". Two motions, relating to traffic volume
information were put to the meeting and were "Lost".
|
|
5 November
2001.
|
Receipt
of report from CSL titled "Weiti Toll Road Option".
|
This
report commissioned by the CEO was "limited to identifying
the key differences between the DIY and BOOT options and assessing
the impact of these differences" The report did not consider
the full financial impact of receipt of the "DIY" Transfund subsidy
for PENLINK.
|
|
15
November 2001
|
Special
Council Meeting Agenda Papers
|
Various
PENLINK matters including the material relating to the withholding
of sensitive commercial information.
|
|
15
November 2001
|
PENLINK
- Expressions of Interest
|
The
CEO report to the Council (in confidence) regarding:
- The
evaluation of expressions of interest.
- The
CEO's recommendation "that the Council should not consider further
the DIY alternative".
- CSL's
report - their "Executive Summary" was tabled.
- Land
purchases for the project were recorded together with approvals
(granted) relating to Powers of Entry to the land.
|
|
6 December
2001
|
Notice
of Motion - Cr Walker - PENLINK
|
Cr
Walker moved for a "possible delay of PENLINK because of lower traffic
volumes on Whangaparaoa Road.". The motion was "Lost".
|
|
6 December
2001
|
Agenda
Paper
|
The
Project Manager - PENLINK tabled the project brief for review.
It was approved for use by the Council. Cr's Rose and Walker had
their opposing votes recorded.
|
|
6 December
2001
|
PENLINK
Expenditure
|
Preliminary
costs to 16 November 2001 of $405,937 and land purchases to the
same date of $845,489 were reported.
|
|
20
December 2001
|
Emergency
Committee Meeting - PENLINK Geo-technical Investigations
|
Approval
was sought for a sum (in addition to the existing PENLINK budget)
of $200,000 to conduct ground drilling etc at the PENLINK site.
Approval was granted.
|
|
31
January 2002
|
PENLINK
Expenditure
|
Preliminary
costs to December 31 2001 of $581,965 - excluding geotechnical costs,
and land purchases expenditures to the same date totalling $2,151,600
were reported.
|
|
5 February
2002
|
Media
Release from the RDC titled PENLINK project update
|
This
media release quoted the RDC's CEO as stating, "that the withdrawal
of Fulton Hogan is not an encouraging development. I believe it
is a signal that the BOOT approach as structured does not have great
commercial margins".
|
|
24
February 2002
|
Press
Release from Cr Walker
|
Cr
Walker includes detailed argument against the PENLINK proposal largely
relating to the lower than expected traffic volumes.
|
Further Commentary
and Events still to unfold.
Generally
the events of the past fifteen months have been useful and helpful in
informing elected members - the decision- makers to come to grips with
this complex project. In general support from Councilors for the project
to proceed - at least to a next stage of the approval process has grown
and has been in evidence at meetings of Council.
But some
disquiet has been expressed by a growing number of Councillors. The more
common grounds for disquiet have been somewhat narrowly confined to some
environmental concerns, the extent of any future liabilities of Council,
the method of proposed funding and assessment of an alternative to PENLINK
- the widening of Whangaparaoa Road.
In addition,
astute observers have noted the emergence of a growing advocacy, a partiality
within the Council that is in favor of the project proceeding although
final judgments are still to be reached. This, as will be discussed and
referred to elsewhere is not an unusual response from proponents of Council
sponsored initiatives such as PENLINK.
Council meetings
and the workshops conducted associated with the project have permitted
a range of opinions, including the authors to be expressed. Not all of
these meetings have been held in public usually because the commercial
confidentiality of the material under discussion has been cited as the
reason for exclusion of the public from the proceedings. As a result,
only Council members themselves, based on advice they have received on
these matters from the Council's solicitors and management and from their
own observations, can judge if these restrictions have been appropriate.
It is not
the business of this report to either take sides in the ongoing debate
nor to question management's and politician's motivations for emergence
of some favouritism. It is competent however and it is the precise purpose
of the S 122C legislation, as it is with the prudent financial
management of Council affairs, and specifically the terms of a S 122C
report, to caution the decision-makers to be very careful to achieve and
insist upon balanced and independent advice particularly for the matters
they remain uncertain about. The complexity and scale of the issues demands
earnest and properly motivated enquiry. The commitments being entered
into are long term and involve huge sums of money. The stakes are high
and as was pointed out in the draft report [ref; page six of Section
7]:
"Elected members must themselves be satisfied, subject
to reasonable residual risk, (concern) that the responses they receive
concerning these issues (the remaining uncertainties) provide them with
an adequate level of comfort. For it is the Council, its elected members
in the final event that would bear the brunt of public criticism if these
issues had not been satisfactorily resolved prior to commissioning the
PENLINK project".
Since the
time that this statement was made, whilst the statement still holds true,
an added pressure upon decision-makers has appeared.
As is so
often the case with projects of this large scale and complexity, the phenomenon
of "inertia" begins to exert itself. As the costs and committed
resources to a project build up, there emerges an understandably human
response from decision-makers and others to these circumstances. The build
up of sometimes uncritical support for a project occurs. The impatience
and inertia to get the process completed very roughly translates into
"a car becoming a truck and then a bulldozer and anyone in the way
had better stand clear". In other words a combination of forces combine
with the potential to cloud the judgments called for.
A perusal
of the table of events and the commentary (above) gives some evidence
of these forces of inertia and of a pro-project advocacy.
The business
of this report in these circumstances is to quite properly sound a caution
and where balanced views are challenged to provide where possible an independent
and informed voice on the matters of residual concern. The content and
timing of this report have been designed to fulfill these functions.
As can be
seen from the commentary of the table, the matters which are dealt with
within the next section of this report, most relating to gaining the "best
deal" are drawn to the attention of elected members. Whatever the
forces at work, including the effects of inertia which will be more fully
described later in this report, elected members must rationally and carefully
progress through the final stages of the processes to their satisfaction.
The issues remain to be finally and fully debated.
|