PENLINK FINAL
S 122C REPORT
The CSL ("Cranleigh's")
report and the subsidy issue
The draft
S 122C PENLINK report reached the conclusion [ref; page 16 of Section
1 Summary of Findings] that:
"Though no complete data has been provided of the RDC 'doing it'
option, it seems that the view that the RDC could not 'do it themselves'
is not the full picture...For if the revenues from tolls more than offset
the costs of servicing PenLink debt and other operating costs then the
RDC 'could do it'. "
After discussions
with the Chief Executive - the "CEO" and Councillors this view was accepted.
As a result of these discussions, which were conducted at a PENLINK Workshop
held on the 8 October 2001, Councillors agreed to obtain further information
and determine what the result would be if the RDC was to do it themselves
- termed the "RDC/DIY" or just the "DIY" option.
To assist
in the measurement of the "DIY" option, the author prepared a document,
[ref: "Specifications of the Rodney District Council Public Sector
Comparator"] the "Specifications" document. These specifications
detailed the information necessary to satisfy the S 122C investigation
requirements.
The document
was forwarded to the Council's CEO who then set out the terms of reference
of this exercise and commissioned the firms of Capital Strategy Ltd and
Cranleigh Strategic Ltd, (CSL) to complete the task.
The firms
reported their findings on 5 November 2001 [ref; CSLs report titled
"Weiti Toll Road Option"] and presented these to a meeting of Councillors
held on that date.
The turn
of events concerned with "the CSL initiative" requires a commentary, as
there were a number of issues that arose which proved to be unsatisfactory.
The terms
of reference produced by the CEO did not completely follow the suggestions
of the "Specifications" document. As a consequence the CSL report
did not fully include findings of significance to the case. The discussions
at a later workshop of the report's findings not surprisingly left a number
of Councillors in doubt on some matters.
This section
of the report attempts to set the record straight on the issues involved,
it highlights the information missing from the CSL report, information
that should have been more fully considered by the decision-makers.
It is first
necessary to clear up the confusion that arose as to the purpose of the
"Public Sector comparator" exercise. [ref; Specifications for the
PSC October 2001] The principal purpose of the exercise was not,
as a number of Councillors appeared to believe, to assess the "DIY" option
in expectation that the RDC would in fact do it themselves.
The purpose
of the exercise was to provide Councillors with a basis for comparison,
a "benchmark" by which they could compare the quality of the BOOT bids,
that is by providing a basis for comparison of the bids with a hypothetical
(or conjectural) "RDC/DIY" option.
This distinction
on the face of it might seem pedantic. Far from it. Councillors must be
aware of what an "RDC/DIY" option would involve in monetary terms. They
will then be fully aware of the value of the rights they are proposing
to cede to the private bidders under the proposed BOOT scheme.
As was perhaps
inevitable, given the ambiguity surrounding the purpose of a "DIY" financial
modeling, much discussion at the workshop concerned the views of those
who for their own valid reasons were opposed to the RDC considering an
actual completion of the project by the Council rather than the
posited conjectural "DIY" solution.
Because of
the uncertainties as to the purpose of the exercise the meeting of Councillors
did not achieve a properly moderated result. What is more important, due
to the nature of the report they did not have the opportunity to assess
the important information that is now produced.
The following
analysis makes the relevant comparisons and shows that the DIY option
produces results that are significantly superior to those that KPMG, the
Council's financial advisors had earlier considered were likely to be
offered by the private funders. Without knowledge of these comparisons
the Council risks achieving less than the "best deal' possible. The
private bids can only be fully and properly evaluated having been benchmarked
against a DIY alternative. This was the objective in specifying the development
of the Public Sector comparator model.
As stated
earlier in this report the impact of receipt by the Council of subsidies
or grants for PENLINK alters the analysis of the project in favour of
a "DIY" option. But the matter of receipt of Transfund and/or other agencies
subsidies or grants and as stated in the CSL report remains uncertain.
The following
observations regarding the CSL analysis are in part based on the assumption
that the full Transfund subsidy would be received if the Council used
its "DIY" option. Whilst this is, as already has been conceded, a matter
of some uncertainty, for the purposes of the comparator exercise, and
consistent with its desired specifications as suggested by the writer
the effects of a subsidy need to be factored in. CSL failed to fully
model the impact of subsidy receipts.
The comparisons
(largely due to the influence of subsidy receipts) are startling. Based
on Council's figures, a "DIY" option compared with a projected equivalent
private funders bid would shorten the tolling period associated with a
private funder by about sixteen years! This is a very significant matter
that was not given sufficient airing when the CSL report was prepared.
To keep the
matters relating to the CSL report and subsidies simple, the details of
the "Specifications" document and of the CSL report are only
selectively quoted, more detail of their contents is contained in the
appendices to this report.
The "Specifications"
for the comparator exercise when comparing the "DIY" option with PENLINK
as proposed, included the statement [ref; page 1 Specifications for
a PSC] that :
"one most important component of the model will be the
inclusion of receipts of subsidies which would accrue to the RDC,
but as advised these would not be offered to a private contractor".
For whatever
reason, either the exercise of CSL's judgment or due to their limited
terms of reference, the main and prominent findings of the CSL report
did not include the effects of the receipt of subsidies.
As a result,
the intended S 122C analysis contained in the "Specifications"
document was not performed. The full notional impact of the receipt of
the Transfund subsidy of $24 M, the accepted detail of which was
taken from and was referred to in the draft report [ref; for example
page 12 Section 7 of the draft report] was not tested or reported
by CSL.
CSL reported
in the following terms within their Executive Summary [ref; pages
3 of the CSL report]:
" The DIY offers a projected pre-tax positive Internal Rate of
Return ('IRR') of 8.8% and would result in a toll of $1.75 being applied
for a period of 22 years"
An IRR of
8.8%, CSL considered might not meet RDC's capital expenditure criteria,
that is, it made the benefits of the DIY appear marginal.
But this
finding did not make any allowance for inclusion of the receipt
of subsidies. Even so it should be noted that without the inclusion of
subsidies the tolling period of the DIY option is shorter (by say ten
years, 32 less 22 years) than is likely from private funding.
Later analysis
of this section of this report demonstrates how a notional inclusion of
the full subsidy would materially alter CSL's principal finding.
CSL did do
some calculations involving inclusion of "a subsidy" of $10
M, although after exhaustive enquiries by the writer of the reports author
it is uncertain why this particular figure was chosen. At page 14 of their
report they stated in terms which can only be described as remarkable
understatement that:
" The possibility of subsidy funding will have a material effect.
We have considered the possibility of the receipt of the sum of $10 million
from a funding source and this significantly reduces the length
of the toll period and improves RDC's balance sheet financing requirement".
(emphasis added).
NOTE: It
might be speculated that the $10 M figure is an estimate of an amount
possibly partially made up from receipts of grants including an amount
received from Infrastructure Auckland. There is a good chance of receiving
some grant(s) of this kind but these have yet to be applied for.
The above
extract was taken from the body of the CSL report. CSL's principal findings,
contained in their executive summary which was widely circulated as a
Council agenda paper were made without reference to or inclusion of the
effects of subsidy receipts. Their report did not fully provide information
on their effect. Their report, whilst on the one hand admitting to the
possibility of subsidy receipts, (above) and stating that they would have
a material effect failed to give any prominence to or measure the (full
$24 M) effects of these.
CSL's exclusion
of the effect of subsidies appears to be based on their belief, as stated
at page 14 of their report that:
"there is a high degree of uncertainty as to whether or not the RDC
would receive subsidy funding for the DIY option".
The question
of this "uncertainty" and its "high degree" is covered
later in this section. Covered also is the need, in spite of any uncertainty
because of the very material size of the subsidy monies involved, to actively
pursue the matter of RDC"s entitlement to PENLINK subsidies.
CSL's analysis
as pointed out was incomplete for the DIY option. Much of the prior work
conducted for the draft S 122C report and the DIY case factored in the
receipt of subsidies. In addition, for matters involving uncertainty
it is not sufficient for the conduct of a full and complete analysis
to merely take one position without demonstrating the effects of the other(s).
This will result in a clouding of the issues and in the worst case a bias
to the findings.
Consequently,
CSL's principal findings have not told the full story. The somewhat marginal
results attributed to the DIY option as reported, for example an IRR of
8.8% as will be shown, would be very different if subsidies had been included.
Arising from
the CSL reporting, from a Councillor (decision-maker's) perspective, the
important point to bear in mind is that their report, which has had the
effect of marginalising the DIY option is that the CSL positions were
reached without factoring in the effect of very significant subsidies,
uncertain or not.
What would
be the results if the full total for subsidies had been included in their
calculations?
As part of
the field work conducted to produce the draft S 122C report, modeling
was conducted, [ref; Internal Memorandum Kevin Ramsay, RDC's Finance
Manager to John Brown dated 14 May 2001].
This study
was conducted to ascertain the financial effects of "the RDC going
it alone" (DIY) for the PENLINK project. The "Ramsey" analysis,
whilst it might vary in some minor matters from that conducted by CSL
is so starkly different from CSL's findings that such variations within
Ramsey's model as might exist, would not invalidate or materially alter
its conclusions. The model was constructed from data provided by Mr. Brown,
the PENLINK project leader.
Again keeping
the detail to a minimum and put very simply this analysis showed:
The "RDC/DIY"
option, without subsidies showed a positive Net Present Value (NPV)
of $29.8 M. In other words the surpluses over a 31 year tolling period
would be this total. Whoever built or operated the PENLINK facility could
expect to enjoy a surplus of about this magnitude though naturally the
party involved would also carry the risks of operational revenue shortfalls
as well.
The RDC however,
if entitled to and in receipt of a subsidy for the project would enjoy
a surplus of over $50 M, for with the full subsidy included the project's
NPV increases to
$51.4 M.
The tolling
period for the facility, roughly equivalent to the period of "payback",
that is the time it would to take to pay off the bridge and cease tolls,
if managed under the "RDC/DIY" option would shorten to about sixteen years,
a period itself some sixteen years shorter than if the PENLINK proposed
BOOT-type funding went ahead.
CAVEAT: As
described in the Introduction to this report no further corroboration/audit
of this data has been conducted. The data is taken unaltered from the
draft report whose particulars were accepted as valid, that is following
their corroboration and they were substantiated by RDC Management at the
time.
These are
very material facts relating to the subsidy matter which are also highlighted
elsewhere in this report. It should be clear from this analysis that
the matter of subsidies is a major, though not the only determinant of
achieving the "best deal". Receipt of a subsidy is by no means
assured but a clear understanding of the reasons for this is essential
to this case.
To state
that, merely because the receipt of subsidies and or grants is not assured
that their effect should be ignored, is unacceptable. The view is unacceptable
because, given the right circumstances and by taking the appropriate actions
the subsidy and or grants for PENLINK could either in total or
in part be secured.
The current
circumstances for claiming a Transfund subsidy were recorded in the CSL
report [ref; page 14] and are these:
The current Transfund evaluation criteria is now 4.0:1, this changed from
3.5:1 in July 2001"
The evaluation
criteria, often termed the benefit to cost ratio alters periodically
and largely reflects the availability of roading funding. The movement
to a 4.0:1 ratio indicates a greater scarcity of funding now than when
the draft S 122C report was prepared.
The draft
report [ref; Section 1 Summary of Findings page 12] recorded the
fact that:
"$24
M would be paid by Transfund as their share of the costs of the Weiti
crossing and related roadworks. It should be noted that the Crossing and
other works meets Transfund's subsidy benefit/cost ratio"
The eligibility
of roading projects for subsidies is subject to variation. The PENLINK
project having been clearly eligible prior to July of 2001 is now borderline
but its circumstances can still alter again in future. For example the
traffic volume counts on Whangaparaoa Road could over time increase to
a point where the project once again moves into the eligibility range.
It would
seem unlikely though not impossible if roading funding is not increased
that the opposite would occur, that is that the project would not attract
subsidy particularly given the continuing population growth being experienced
on the Peninsula. But in spite of this, if the PENLINK benefit to cost
ratio was to make PENLINK remain ineligible for subsidies, then this may
be a good reason to seriously question the need for the facility at all!
After all, a ratio of this nature does carry with it some assurance that
a project is worthy of proceeding with.
The Transfund
benefit to cost cut-off could rise or fall due to funding variations.
The fluctuations of funding are not readily predictable but the influences
upon them can be identified and some idea given of the chances of an improvement
of the situation.
Transfund's
financial capability to provide roading subsidies is dependent upon the
transfer payments they derive from road user charges, excise duties and
motor vehicle registration fees. [ref; Funding for Land Transport
System] Over the last five years the nationwide benefit/cost ratio
has measured on average 3.6:1. Alterations to Transfunds mandate, added
sources of roading funding (from increases in the petrol tax) and a new
funding regime are all mooted within imminent policy announcements and
are discussed elsewhere in this report.
The circumstances
of subsidy eligibility for PENLINK are therefore uncertain but it is suggested
not sufficiently uncertain as to exclude them from consideration
within financial and other analysis.
Having been
eligible "last year" it would not take major movements of the
(existing, let alone future) measurement criterion in the short to medium
term to again achieve eligibility.
In spite
of the loss of subsidy monies some allowance might be made in effect a
premium added to PENLINK's benefits by proponents of the project for building
PENLINK "now" rather than waiting for a subsidy at some future
indefinite time - when the project became eligible. This may be understandable
given the support that appears to be present for getting the project completed.
Elected members need however to carefully weigh the merits of the bridges
possible earlier completion against the loss of the subsidy, that would
as a consequence be foregone.
|