Ph: 09 422 0598
Ph: 0274 792 328
larry@kauriglen.co.nz
 
 

 

 

 

 

 

 

Perlink Final Report

Introduction
The report (the cost/benefit analysis) represents the culmination of over two years of effort. With updates events affecting the project to February 2002. Much has occurred in the intervening period.

Decision Time "The Final Word"
The final word identifies the remaining key issues presented for the consideration of elected members - the decision makers.  The Section is intended to focus the final decision making process upon those matters which most will influence a decision.


Events affecting PENLINK and occurring since November 2000
Reporting of the events and issues associated with a project or proposal, will over time have to deal with
"a moving target". The events concerned with PENLINK have been very protracted as is the evidence from the draft report that covered a period of at least five years
.

The CSL (Cranleigh's) Report and the subsidy issue
As a result of these discussions, which were conducted at a PENLINK Workshop held on the 8 October 2001, Councillors agreed to obtain further information and determine what the result would be if the RDC was to do it themselves - termed the "RDC/DIY" or just the "DIY" option.

Impending Government Transport Policies
The present law relating to subsidy payments is highly unsatisfactory due to its inequities and the irrational (in an economic sense) application of Transfund subsidies.  The present circumstances give rise to the motorist paying twice - the so termed "double-dipping".

Whangaparaoa Road "Widening"
The widening option has been cast by its critics as a greatly inferior option to PENLINK due mainly to the very major impact that widening on the large scale required would have on numerous private properties.